RAUHES HUS MYK FORBINDELSE HAMBURG-HORN
OTTO WULFF Bauunternehmung GmbH
Prosjektbilder
Prosjektbeskrivelse
For Hamburger Hochbahn AG, OTTO WULFF has implemented a vibration-isolating track support plate in the tunnel structure of the U-Bahn line U4/U2 directly behind the Rauhes Haus station heading towards the city center.
The goal was to isolate the above-ground buildings from the vibrations caused by the trains passing every 5 minutes. For this purpose, approximately 230 height-adjustable spring elements were installed to create a mass-spring system, in order to raise the 600 m², 40 cm thick reinforced concrete plate by 4 cm and permanently separate it from the rest of the U-Bahn tunnel structure.
Within 14 days, the track support plate had to be completed and load-bearing during the prescribed maintenance period, ready for rail installation and train traffic. Thanks to great teamwork and the cooperative collaboration with the client and the contractor, train operations could resume as planned.
Om OTTO WULFF Bauunternehmung GmbH
I mer enn 90 år har vi som familiebedrift stått for kvalitet, pålitelighet og ansvar – for mennesker og eiendommer.
🏠 Vi dekker hele verdikjeden: Fra tomtekjøp og planlegging til utvikling, bygging,...
OTTO WULFF Bauunternehmung GmbH ansetter også
Statistikk
670 ansatte
Ansatte
42 år
Gjennomsnittsalder for ansatte
1-2 år
Gjennomsnittlig prosjektid
12 km
Gjennomsnittlig avstand til byggeprosjekter
36 prosjekter
Aktive byggeprosjekter