OTTO WULFF Bauunternehmung GmbH

ROUGH HOUSE SOFT CONNECTION HAMBURG-HORN

OTTO WULFF Bauunternehmung GmbH

Infrastructure & Earthworks

Project Images

Project Description

For the Hamburger Hochbahn AG, OTTO WULFF, on behalf of Bahnbau Nord GmbH, has implemented a vibration-isolating track support plate in the tunnel structure of the U4/U2 subway line directly behind the Rauhes Haus station heading towards the city center.

The goal was to isolate the above-ground buildings from the vibrations caused by the trains passing every 5 minutes. For this purpose, approximately 230 height-adjustable spring elements were installed to create a mass-spring system, allowing the 600 m², 40 cm thick reinforced concrete plate to be raised by 4 cm and permanently decoupled from the rest of the subway tunnel structure.

Within 14 days, the track support plate had to be completed and load-bearing during the prescribed maintenance period, ready for rail installation and train traffic. Thanks to great teamwork and the collaborative cooperation with the client and the contractor, train operations were resumed as planned.

See original text

About OTTO WULFF Bauunternehmung GmbH

Learn more about the company behind the opportunity
OTTO WULFF Bauunternehmung GmbH
OTTO WULFF Bauunternehmung GmbH

For over 90 years, we've been a family business known for quality, reliability, and responsibility – for people and properties.

🏠 We cover the entire value chain: from land acquisition and planning...

See original text

OTTO WULFF Bauunternehmung GmbH also employs

Project ManagerConstruction ManagerForepersonProject Construction ManagerBauleiter*in HolzhybridbauBricklayer*in RenovationCrane technicianCalculator*in Infrastructure ConstructionConstruction Site ManagerConcrete and reinforced concrete builder

Key data

670 employees

Employees

42 years

Employee Average Age

1-2 years

Average project time

12 km

Average distance to construction projects in km

36 projects

Active Construction Projects

Project Details