Pressure line and pumping station for the Burger Str. clinic, including a shotcrete excavation pit

Gustav & Otto Müller GmbH & Co. KG

Sewer & Pipeline ConstructionInfrastructure & EarthworksRoadworks

Project Images

Project Description

A sewage pumping station with a collection shaft was built on the grounds of the Sana Clinic, from which the wastewater from the catchment area is fed through a PE-HD pressure pipe into a transfer structure on Burger Straße. A second and third pressure pipe serve as backups.

The special thing about this project was the elliptical reinforced concrete excavation pit, the large precast concrete parts, the tight space in the connection area of Burger Straße for the transfer structure, and the HDD horizontal directional drilling.

See original text

About Gustav & Otto Müller GmbH & Co. KG

Learn more about the company behind the opportunity
Gustav & Otto Müller GmbH & Co. KG
Gustav & Otto Müller GmbH & Co. KG

We are Gustav & Otto Müller GmbH & Co. KG and we're looking for new people to join our team. If you're up for real construction projects and a company that mixes tradition with a chill work vibe, then...

See original text

Gustav & Otto Müller GmbH & Co. KG also employs

Site managerSite managerApprenticeForemanForemanskilled workerskilled workerTruck driver

Key data

30 km

Average distance to construction projects in km

10 projects

Active Construction Projects

40 employees

Employees

1-12 months

Average project time

15,000,000 €

Annual construction volume in €

Civil Engineering, Service Work, Engineering Structures, Rolled/cast asphalt

Project Types

Project Details

Location

Remscheid, Germany

Burger Straße