Preparatory measures:

  • Construction of a sheet pile wall in the area of the abutments to secure the construction pits

Demolition work:

  • Demolition of the platform, the underground platforms, the track bridges including abutments, the walls of the technical rooms and dismantling of tracks 12/13

New construction:

  • Staircase descent to the pedestrian underpass
  • Assembly of the WIB beams for the superstructure of the track bridges laid on prefabricated end cross beams and concreted after the reinforcement has been installed
  • Installation of the transition construction chamber wall - superstructure and connection to the existing structure longitudinally (underground platforms)
  • Installation of the platform bridge in 3 parts including transition construction
  • Construction of platform edges in conventional construction
  • Installation of tracks 12/13 and connection to the existing structure
  • Covering of the platform bridge with natural stone flooring on screed
  • Staircase descent to the pedestrian underpass with block steps made of concrete, cladding of the wall surfaces of the staircase descent with natural stone flooring, mounting of the platform equipment
See original text

About KASSECKER

Learn more about the company behind the opportunity
KASSECKER
KASSECKER

KASSECKER stands for future-oriented competence in construction. With over 560 employees, we work on projects across regions in the business areas of high-rise and industrial construction, civil and p...

See original text

KASSECKER also employs

Skilled Worker for Concrete and Reinforced Concrete Construction (m/f/d)Foreman in High-rise and Industrial Construction (m/f/d)Construction Drafter/Building Technician in Civil and Industrial Construction (m/f/d)Calculator (m/f/d)Buyer (m/f/d)Foreman in Deep and Pipeline Construction (m/f/d)Foreman in Railway and Civil Engineering (m/f/d)Site Manager in Civil and Pipeline Construction (m/f/d)Foreman in Deep and Pipeline Construction (m/f/d)Foreman in Railway and Civil Engineering (m/f/d)Show all

Key data

560 employees

Employees

65 projects

Active Construction Projects

113,000,000 €

Annual construction volume in €

39 years

Employee Average Age

Project Details